RE Onboarding & Offboarding System: Comprehensive Alignment Report

Prepared for: Dealer Onboarding Project

Reference: SRS v1.4 / 2.0 (High-Fidelity)

Current Date: April 1, 2026


1. Executive Summary: Full Project Scope

This report covers the end-to-end alignment of the Dealer Lifecycle Management system, spanning Onboarding, Offboarding (Resignation/Termination), and Self-Service (Constitutional Change/Relocation).

Goal SRS Section System Status Completion %
Dealer Onboarding Section 6 Stable Flow (Eval -> LOI -> SAP) 85%
Dealer Resignation Section 7 Backend Ready; UI in progress 50%
Dealer Termination Section 8 Logic Ready; SCN Flow in progress 40%
F&F Settlement Section 10/11 Trigger Ready; Clearance Grid Pending 20%
Self-Service (Constitutional) Section 12.2 PENDING (Schema Ready) 10%
Self-Service (Relocation) Section 12.2.6 PENDING (Schema Ready) 10%

2. Onboarding & Evaluation (Section 6)

Owner: DD Admin / DD ASM

Sub-Task Demarcation Points Status Integration
Questionnaire Weighted Scoring (100%), Public Link Access COMPLETED Real
Shortlisting Bulk Action, Assign to ASM/ZM COMPLETED Real
Interviews (L1-3) Panel Scheduling, KT Matrix, AI Summary COMPLETED AI Mocked
FDD Verification Agency Upload, Report Review by DD Head 🚧 IN PROGRESS Manual
LOI Issuance 3-tier Approval (Finance/DD-Head/NBH) COMPLETED PDF Mocked
Security Details BG & Deposit Verification (BG / SD) 🚧 IN PROGRESS Pending UI
Site Readiness Arch Blueprints, Statutory Docs, Dealer Code COMPLETED SAP Mocked
Go-Live LOA Issuance, EOR Checklist 🛑 PENDING Logic Only

3. Dealer Lifecycle & Self-Service (Section 12)

Owner: Dealer (Initiation) / Legal & DD Head (Approval)

3.1 Dealer Resignation (Section 12.1)

  • Width: Outlet-level selection, Last Working Day (LWD) capture, Withdrawal logic.
  • Status: Backend endpoints for initiation are ready. UI needs the "Resignation Dashboard" for the dealer persona.

3.2 Constitutional Change Management (Section 12.2)

  • Width: Proprietorship → Partnership/LLP/Pvt Ltd.
  • Depth: Dynamic document checklist (GST, PAN, Partnership Deed, COI, MOA/AOA).
  • Status: PENDING UI. Schema supports the different constitution types, but the multi-level internal review (ASM → ZBH → Legal) needs workflow orchestration.

3.3 Relocation Request (Section 12.2.6)

  • Width: New Site Selection (Manual/Map), Distance Tracking, Property Docs.
  • Depth: 4 Categories of Docs (Property, Legal, Statutory, Infrastructure).
  • Status: PENDING UI. Approval hierarchy (ASM → RBM → ZM → NBH) is partially mapped in the assessment controller logic but requires a dedicated controller.

4. Administrative & Shared Modules (Section 9)

Owner: Super Admin

Feature Detailed Breakdown Status
RBAC Zone/Region/Area cascading hierarchy; National Role visibility. COMPLETED
Opportunity Window-based Geography opening (State/City/District). COMPLETED
SLA Config Warning/Escalation thresholds per stage. 🚧 IN PROGRESS
Email Templates Trigger-based logic (Interview Scheduled, LOI Issued). 🚧 IN PROGRESS
Audit Trail Entity-level history (what changed, by whom, old vs new). COMPLETED

5. Mocks & System Simulations

Item Description Status
SAP Master Simulates code generation (Sales/Service) and status sync. MOCKED
Gemini AI Simulates consensus summary paragraph generation. MOCKED
WhatsApp/SMS Simulated via console logs for non-sensitive alerts. MOCKED
Meeting Links Mock Google Meet link generation. MOCKED

6. Project Roadmap & Critical Gaps

  1. F&F Settlement Clearance Grid: The most complex remaining logic—capturing clearance from 16 departments.
  2. Legal Letter Engine: Moving from "Marked as Generated" to real PDF generation with templates.
  3. EOR Checklist Integration: Enabling the ASM to perform the final "On-Site" check via the mobile/web interface.

Status Legend:

  • COMPLETED: Logic, UI, and Backend aligned.
  • 🚧 IN PROGRESS: Development underway; partially functional.
  • 🛑 PENDING: Logic defined in SRS but not yet implemented.