RE Workflow Management System - Task Timeline
SSO-Based Authentication | Realistic Progress Tracking
Version: 2.0
Date: October 23, 2025
Authentication: SSO via RE SSO Bridge (No login/signup screens)
Current Status: Frontend UI 80% extracted, Backend 70% setup
🎯 Current Project Status
Overall Progress: 10%
- Backend: 10% (repo 70% setup, database 0%, APIs 0%)
- Frontend: 16% (UI 80% extracted, but no functionality)
Reality Check:
✅ What We Have:
- Frontend UI components from Figma (80% extracted, mobile responsive)
- Work notes UI + partial functionality (emoji, document selection working)
- Dependencies installed
- Repository structure in progress
❌ What We DON'T Have:
- No Redux store created
- No API service layer
- No form validations
- No API integration
- No business logic
- No authentication working
- No database setup
Translation: Having UI ≠ Having features. We have the "look" but not the "functionality."
🔐 SSO Authentication (No Login Screens)
How SSO Works:
- User visits app → App redirects to RE SSO Bridge
- User logs in with RE credentials (handled by SSO)
- SSO redirects back to app with token
- App validates token, syncs user from Active Directory
- User lands on dashboard (logged in)
What We Build:
Frontend (1.5 days):
- SSO callback handler page
- Protected route guards
- Logout button
Backend (2 days):
- SSO OAuth2 integration
- User sync from Active Directory
- JWT session management
No Need For:
- ❌ Login page
- ❌ Signup page
- ❌ Password reset pages
- ❌ Email verification
📅 Week-by-Week Timeline (10 Weeks)
Week 1 (Completed): Sprint 0 Setup
- ✅ Frontend UI extraction 80% (Figma)
- 🔄 Backend repo setup 70%
- ❌ Database: Not started
- ❌ Redux: Not created
- ❌ API layer: Not configured
Week 2 (CURRENT): Complete Foundation
Backend (3 days):
- 🔥 Database schema setup (1 day) ← CRITICAL
- Express + middleware configuration (0.5 days)
- Sequelize ORM + models (1.5 days)
Frontend (4 days):
- Complete UI extraction 20% remaining (1 day)
- 🔥 Setup Redux store + 8 slices (2 days) ← CRITICAL
- 🔥 Configure Axios API layer (1 day) ← CRITICAL
Target: Foundation ready for feature development
Week 3: SSO Authentication
Backend (2 days):
- SSO Bridge OAuth2 integration
- User sync from Active Directory
- JWT token generation
- Auth APIs
Frontend (1.5 days):
- SSO callback page
- Protected routes
- Logout button
- User profile display
Target: Users can login via SSO
Week 4: Workflow Creation Wizard (Part 1)
Backend (4 days):
- Workflow CRUD APIs
- Approval levels APIs
- User search API
- TAT calculation logic
Frontend (4 days):
- Template selection (connect to Redux)
- Basic information form (validation)
- Approval workflow builder (complex!)
- Dynamic levels
- User @mention search
- Real-time TAT calculation
Target: First 3 wizard steps functional
Week 5: Workflow Creation Wizard (Part 2)
Backend (3 days):
- Participant management APIs
- Document upload APIs (GCP storage)
- Workflow submission logic
Frontend (4 days):
- Participants step (spectator @mention)
- Documents step (drag-drop upload)
- Review & submit step
- Multi-step API integration
Target: Complete workflow creation working
Week 6: Request Management
Backend (4 days):
- Workflow listing APIs (filters, search, pagination)
- Approval/rejection APIs
- TAT tracking service
- Activity logging
Frontend (4 days):
- My Requests page (tabs, search, filter)
- Open/Closed Requests pages
- Request detail page (Overview tab)
- TAT progress bar component
Target: Users can view all their requests
Week 7: Approval Actions
Backend (3 days):
- Approve/reject workflow logic
- TAT monitoring cron job (every 30 min)
- Notification system (8 types)
Frontend (4 days):
- Workflow tab (approval timeline)
- Documents tab (preview, download)
- Activity tab (timeline)
- Approve/Reject modals
Target: Users can approve/reject requests
Week 8: Collaboration Features
Backend (4 days):
- Work notes APIs (@mentions)
- Document preview/download
- Activity timeline APIs
Frontend (2 days):
- Connect work notes to backend
- Connect document APIs
- Notification bell with polling
Target: Work notes and documents working
Week 9: Dashboard & Analytics
Backend (3 days):
- Dashboard statistics APIs
- AI conclusion generation
- Workflow closure API
Frontend (4 days):
- Dashboard with charts
- Search & filter components
- Conclusion display & edit
- Closure functionality
Target: Dashboard and AI conclusions working
Week 10: Testing & Deployment
Backend (4 days):
- Unit tests (Jest)
- Integration tests
- API documentation (Swagger)
- Deployment setup
Frontend (4 days):
- Component tests (Vitest)
- Integration tests
- Performance optimization
- Production build & deployment
Target: Production launch! 🚀
📊 Task Summary
Backend: 25 Tasks
- Sprint 0: 4 tasks (3 days)
- Sprint 1: 2 tasks (2 days) - SSO
- Sprint 2: 4 tasks (8 days) - Workflow creation
- Sprint 3: 3 tasks (6 days) - Approvals & TAT
- Sprint 4: 3 tasks (5 days) - Documents & Work notes
- Sprint 5: 3 tasks (4 days) - Dashboard & AI
- Sprint 6: 6 tasks (8 days) - Testing & deployment
Total: ~8 weeks (42 days)
Frontend: 30 Tasks (Reduced - No login screens!)
- Sprint 0: 5 tasks (4 days) - Foundation
- Sprint 1: 3 tasks (2.5 days) - SSO callback
- Sprint 2: 8 tasks (9 days) - Workflow wizard
- Sprint 3: 9 tasks (10 days) - Request management
- Sprint 4: 4 tasks (5 days) - Collaboration
- Sprint 5: 4 tasks (4 days) - Dashboard
- Sprint 6: 4 tasks (5 days) - Testing
Total: ~8 weeks (40 days)
🎯 This Week's Priorities (Week 2)
Backend Must Complete:
- 🔥 Database schema - Blocks everything (1 day)
- Express.js configuration (0.5 days)
- Sequelize ORM + all models (1.5 days)
Frontend Must Complete:
- Complete UI extraction 20% (1 day)
- 🔥 Setup Redux store + 8 slices - Cannot skip (2 days)
- 🔥 Configure Axios API layer - Cannot skip (1 day)
End of Week 2: Both teams ready for feature development
📋 Core Features Focus
1. Workflow Creation (Week 4-5) - CORE FEATURE
- 6-step wizard
- Approval hierarchy builder (dynamic levels, @mention, TAT)
- Document upload
- Submit workflow
2. Approval Actions (Week 6-7) - CORE FEATURE
- Approve/reject with comments
- TAT tracking (working days vs calendar days)
- Notifications
- Activity timeline
3. Collaboration (Week 8) - CORE FEATURE
- Work notes (chat with @mentions, emojis)
- Document management
- Real-time notifications
4. Analytics (Week 9) - SECONDARY
- Dashboard with charts
- AI-powered conclusions
- Search & filters
📖 Documentation References
⚠️ Key Insights
- SSO = No login screens (saves 3-4 days frontend work)
- 80% UI ≠ 80% done (actually 16% of total work)
- Integration is 80% of work (Redux, API, validation, logic)
- Focus on core features (workflow creation, approvals, work notes)
🚀 Success Metrics
Week 2: ✅ Foundation complete (database + Redux)
Week 3: ✅ SSO authentication working
Week 5: ✅ Can create workflows
Week 7: ✅ Can approve/reject
Week 9: ✅ All features functional
Week 10: ✅ Production deployment
Prepared By: .NET Expert Team
Target Launch: End of December 2025
Current Progress: 10% Complete
Focus: Core workflow features (creation, approvals, collaboration)